Publications / References
Pressroom

Light Rail Construction

Construction Updates

October 6, 2008:

The wetlands mitigation contract awarded to Higgerson Buchanon in January 2008 is now substantially complete. The contractor has completed the planting of all materials for the project, and has installed a protective goose fence has been installed to facilitate successful growth during Fall 2008.

Bryant Contracting, Inc. continues its aerial structure work with pile driving of the structure trestle base piers, forming of concrete pier caps, and placement of bridge beams. They are making rapid progress with the pile driving activity and have completed work on the piers east of Norfolk Southern Railway’s Lambert's Point Branch all the way to Claiborne Avenue.

The bridge approach wall and embankment near NSU are complete. Fabrication is underway for the long track and platform spans across Brambleton Avenue. Overall, this contract is 50 percent complete.

Skanska Civil USA Southeast began its major civil contract work in January 2008 and is responsible for the work on the former Norfolk Southern Railway right-of-way on the eastern portion of the project. Demolition of the existing railroad track is complete, and pile driving for the bridge piers over Norfolk Southern Railway’s Sewell’s Point Branch is complete. Installation and pouring of the Overhead Catenary System foundations behind NSU and other graded locations are also underway. Skanska has completed the removal of the track deck of the Broad Creek bridge and is currently removing the timber piling in the creek bed. The contract is approximately 13 percent complete

Skanska Civil USA Southeast also has the major civil contract in the downtown area of Norfolk, awarded in May 2008. The contract covers utility work, track construction, traffic signals and pavement markings, as well as street and sidewalk paving throughout downtown.

The project also includes a marine bridge at Smith Creek. Skanska has mobilized for its initial bridge construction in the Smith Creek area and began demolition work at Harbor Park. One of the largest floating cranes on the East Coast, nicknamed "Hercules", is easily seen from the Brambleton Avenue bridge over Smith Creek.

Click here to view the latest presentation on the light rail construction progress.

Construction Alerts

HRT provides regular updates about traffic detours and other changes that may affect residents, businesses and commuters. Visit the Construction Alert page for more information.

Outreach Coordinators

If you are a resident, business or property owner near The Tide light rail system, your first point of contact is the Outreach Coordinator. Outreach Coordinators are available to answer questions, to provide construction updates, and to distribute project information.

You can find out more about the Outreach Coordinators and the overall public information campaign, by visiting: Staying Informed.

Construction Safety Tips

During light rail construction it may be more challenging to get in and around the areas near The Tide alignment. HRT is committed to making sure that everyone who interacts with the light rail system does so safely. This includes construction contractors as well as motorists, bicyclists, pedestrians, and children walking to and from school. HRT cares about your safety. Please take a moment and review these construction safety tips:


If you would like to schedule a light rail safety presentation at your school, organization or community event, contact the Public Information Office at 757-222-6000 ext. 6291.

Set an example by obeying the rules and sharing the message: "Stay Alert, Don't Get Hurt!"